Thursday, September 29, 2011
Output Power Issues
As of today, Thursday, Sept. 29th we at 10% power output. It looks like I have a failing final output tube. This will speed up my efforts to install the new solid state transmitter we took delivery of yesterday. Please bear with us. Over the next week our signal will be weaker and probably next weekend we will get the new system installed. Thanks in advance for your understanding. These upgrades will help us in the future.
Sunday, August 7, 2011
Future Upgrades, Outages and Changes
In the next 3 months expect some hiccups in our broadcast signal as we make upgrades for hardening our main and backup transmitter sites. Here is a quick synopsis.
1. We have a new transmitter building for our backup in Duson. As of now I am moving all things into that building.
2. In the next few weeks I will turn off the HD signal so that transmitter can be moved to the backup site and then put in the analog mode so it can run as a backup while a new transmitter is installed into the main site in Maxie.
3. After a new main transmitter is installed in Maxie then I will move the old analog transmitter to the backup site in Duson.
4. All this should take a few months and you should expect no downtime on the analog signal, but the HD signal will be down for a while.
5. Please be patient as this will improve reliability overall for the future.
Tuesday, May 31, 2011
Podcast Issues and Network Outage
Last Saturday we had a campus wide network outage for a few hours which interrupted our stream. That is why the stream was not available.
Then Sunday morning the computer I use for podcast recordings and uploads retired unexpectedly. It was 8 years old and I revived it many times in the past but it finally gave up.
Today another computer takes its place. We'll try to get as many podcasts as we can back on line.
Then Sunday morning the computer I use for podcast recordings and uploads retired unexpectedly. It was 8 years old and I revived it many times in the past but it finally gave up.
Today another computer takes its place. We'll try to get as many podcasts as we can back on line.
Sunday, February 6, 2011
Analog Full Power Reliability and HD Woes
Finally got the correct parts to bring full reliability to our analog transmitter. So full power should be strong and solid. The HD transmitter however, still has issues. I am awaiting return of our HD encoder from the manufacturer. Once received I will get it installed as quickly as possible.
We are awaiting arrival of our new transmitter shelter for the backup site. Once that is done then I will be ready for a new main transmitter. Look for good things ahead for KRVS.
Subscribe to: